Blog 7

Image
For the work period of March 9 - March 23, what work toward your team's project has been completed?   The team has focused on having everything ready for completing validation once the uprights are done being machined. The team has worked alongside the suspension team in the manufacture of the other components the upright will have an interaction with. The team has received CNC’d bell cranks and spacers that are fundamental to the suspension system. The team has also installed the sway bar and pushrod components into the chassis. With all of these components installed and finished, the last step in the suspension geometry validation is to install the uprights. For the work period of March 24 - April 6, what is your team's plan for near term work?  What major milestones does the team hope to achieve in your work?  Since the team experienced yet another unexpected delay with machining, the team expects to have the finalized uprights by March 29. In the following week, the team